Bid Date |
Project
Number and Name |
Contractor
|
Base
Bid
|
Alternates
|
Awarded
|
| 1-7-03 | 02-215 University Courts Replacement Housing, Demolition, BSU, Boise, Idaho | Wallace Brothers Sand & Gravel | $297,501 | ||
| Magnum Contractors | $202,560 | ||||
| Asbestos Abatement, Inc. | $196,690 | ||||
| Northwest Technologies | $262,435 | ||||
| 1-7-03 | West Campus, BSU, Nampa, Idaho | Click Here | |||
| 2-25-03 | 02073 Modular Work Release Center, SICI, Boise ID, Package 1, Site Work |
Hamilton Builders | $78,866 | 1. $5,983 | |
| Paul Construction | $77,348 | 1. $11,700 | |||
| West Regional Contractors | $94,712 | 1. $13,316 | |||
| DeBest | $60,998 | 1. $6,000 | |||
| Gafford Construction | $70,411 | 1. $5,958 | |||
| Kepha Construction | $70,849 | 1. $7,064 | |||
| Wright Brothers | $94,843 | 1. $5,300 | |||
| 2-25-03 | 02073 Modular Work Release Center,
SICI, Boise ID, Package 2, Modular Building |
GE Capital/Design Space | $266,468 | 1. $11,596 | |
| US Modular | $207,500 | 1. $5,250 | |||
| 10-1-03 (ak) | 03-511 Audio/Visual Upgrade, POST Academy, Meridian, Idaho | Marshall Industries, Inc. | $22,121 | 1. $20,714 2. $1,294 3. $3,250 4. $9,722 |
|
| AA Tronics | $18,340 | 1. $18,340 2. $413.92 3. $1,237.90 4. $3,877 |
|||
| Towne & Country Electric | $21,837.21 | 1. $20,586.07 2. $1,487.31 3. $12,828.02 4.$15,259.11 |
10-02-03 | ||
| 9-10-03 (ak) | 04-090 Reroof Scott's Building, CSI, Twin Falls, Idaho | Robison Roofing | $31,375 | ||
| Modern Roofing | $32,380 | ||||
| Smith Roofing | $29,231 | 9-18-03 | |||
| Summit Associates | $35,200 | ||||
| Wilson Roofing | $42,020 | ||||
| ProTech Roofing | $36,754 | ||||
| Upson Roofing | $45,084 | ||||
| Western Roofing | $41,190 | ||||
| Briggs Roofing | $43,890 | ||||
| Covenant Construction | $61,000 | ||||
| Roman Roofs | $48,947 | ||||
| 8-26-03 (ak) | 02-601 Sidewalk Replacement/Curb Cuts, Veterans Services, Boise, Idaho | Seufert Construction | $31,930 | 1. $3,000 2. $ 900 |
|
| Gafford Construction | $31,031 | 1. $5,671 2. $ 540 |
|||
| K-J Corporation | $39,605 | 1. $4,320 2. $1,200 |
|||
| Perkins Construction | $31,100 | 1. $1,250 2. $1,390 |
9-8-03 | ||
| 8-12-03 (ak) | 02-240 Restroom Renovations (10), ISU, Pocatello, Idaho | Brennan Construction | $48,586 | 1. $10,678 | |
| Rivers West Construction | $54,762 | 1. $11,079 | 8-29-03 | ||
| Vern Clark Construction | $56,290 | 1. $16,545 | |||
| 7-31-03 (ak) | 03-226 Accelerator Building Addition, ISU, Pocatello, Idaho | Bateman-Hall | $2,033,000 | 1.$147,000 2.$107,000 |
|
| Harris Construction | $2,127,000 | 1.$139,000 2.$ 95,000 |
|||
| Interwest Construction | $2,241,000 | 1.$158,000 2.$ 74,000 |
|||
| Ormond Builders | $1,975,720 | 1.$138,237 2.$131,396 |
|||
| RE Beck Construction | $1,927,817 | 1.$147,068 2.$104,688 |
8-29-03 | ||
| SE/Z Construction | $2,012,785 | 1.$224,905 2.$237,231 |
|||
| 7-28-03 (ak) | 02-280 Bus Shelters/Turn-Out Lane, BSU, Boise, Idaho | ANCO Construction | $251,582 | 1. $28,375 2. $28,375 3. $28,375 4. $28,375 5. $4,200 6. $1,380 |
|
| K-J Corp., Inc. | $283,100 | 1. $35,200 2. $35,500 3. $34,200 4. $34,400 5. $2,700 6. $800 |
|||
| Wright Brothers | $246,758 | 1. $25,667 2. $25,723 3. $25,020 4. $25,194 5. $0 6. $1,210 |
|||
| Perkins Construction | $270,000 | 1. $25,000 2. $25,000 3. $24,500 4. $24,800 5. $4,500 6. $1,200 |
7-31-03 | ||
| 7-24-03 (ak) | 02-353 Remodel of State Lab (BSL-3), Dept. of Health & Welfare, Boise, Idaho | ANCO | $1,076,00 | 1. $67,500 2. $71,679 3. $71,467 4. $12,734 5. $14,569 6. $21,100 7. $22,028 8. $23,008 |
|
| SE/Z Construction | $1,024,662 | 1. $61,203 2. $74,763 3. $74,723 4. $12,224 5. $12,147 6. $19,460 7. $15,532 8. $20,169 |
7-31-03 | ||
| Engineered Structures | $1,134,000 | 1. $62,000 2. $80,500 3. $80,500 4. $14,000 5. $13,000 6. $20,000 7. $20,500 8. $17,000 |
|||
| W T Seufert | $1,020,000 | 1. $60,850 2. $99,500 3. $99,500 4. $22,000 5. $12,350 6. $19,350 7. $19,000 8. $14,850 |
|||
| Wright Brothers | $1,228,870 | 1. $65,190 2. $107,176 3. $107,174 4. $22,913 5. $12,882 6. $20,872 7. $21,481 8. $32,409 |
|||
| K-J Corp. | $1,073,060 | 1. $64,750 2. $109,325 3. $108,660 4. $23,400 5. $13,700 6. $21,700 7. $20,000 8. $22,400 |
|||
| Guho Corp. | $1,300,000 | 1. $70,000 2. $85,000 3. $84,000 4. $12,000 5. $13,000 6. $22,000 7. $13,500 8. $32,000 |
|||
| 7-18-03
8-21-03 |
01-194 West Campus Academic Building, Boise State University, Nampa ID | For bid results, please contact CM Company, 208-384-0800, or Click Here and see also Here for rebid results | |||
| 7-16-03 (ak) | 01-222 Classroom/Multi-Use Complex, Idaho State University, Pocatello, Idaho | For bid results, please contact Brennan Construction, (208)232-0613 | |||
| 7-10-03 | 99-092 Fine Arts Addition, College of Southern Idaho, Twin Falls, Idaho | For bid results click Starr Corp or at (208) 733-5695 | |||
| 7-1-03 (ak) | 03-250 Reroof Administration Bldg., UOI, Moscow, Idaho | Pacific Tech Construction | $698,000 | 1. $7,500 | |
| Upson Company | $972,950 | 1.$ 11,240 | |||
| Krueger Sheet Metal | $728,151 | 1. $6,263 | |||
| Quality Tile Roofing, Inc. | $1,123,409 | 1. $9,600 | |||
| Cobra Roofing Services | $615,000 | 1. $7,000 | |||
| Burton Construction | $584,236 | 1. $3,798 | 8-1-03 | ||
| 6-24-03(ak) | 03-130 Reroof Technical Bldg., EITC, Idaho Falls, Idaho | Briggs Roofing | $216,520 | ||
| Quality Tile Roofing | $246,992 | ||||
| Smith Roofing | $186,822 | ||||
| Robinson Roofing | $153,000 | 6-30-03 | |||
| Wilson Roofing | $221,818 | ||||
| Modern Roofing | $209,946 | ||||
| 6-24-03 (ak) | 03-531 Clinic Area Build-Out,
DJC, Nampa, Idaho |
Luekenga Construction, Inc. | $186,193 | 1. $14,833 2. $5,989 |
|
| W.T. Seufert Construction | $196,750 | 1. $10,360 2. $2,800 |
|||
| K-J Corporation, Inc. | $207,000 | 1. $10,107 2. $5,362 |
|||
| Ronald W. Van Aucker, Inc. | $166,940 | 1. $14,912 2. $6,677 |
6-9-03 | ||
| Ellsworth Kincaid, Inc. | $179,974 | 1. $11,393 2. $3,719 |
|||
| Brice Construction | $179,800 | 1. $10,485 2. $5,900 |
|||
| BCI Construction | $199,750 | 1. $15,250 2. $6,250 |
|||
| 6-19-03 (ak) | 02-336 Grangeville Armory Remodel, Military Division, Grangeville, Idaho | CamCo Construction | $391,686 | 1. $11,369 2. $3,142 |
7-10-03 |
| Keneston Corp. | $412,023 | 1. $14,760 2. $2,110 |
|||
| Teel Construction | $440,241 | 1. $13,869 2. $680 |
|||
| Wimer construction | $445,000 | 1. $14,912 2. $340 |
|||
| Citadel Construction | $448,422 | 1. $10,528 2. $3,630 |
|||
| Arnen Construction | $449,922 | 1. $14,912 2. $340 |
|||
| 6-19-03 (ak) | 02-531 Install Cooling System, Laundry Bldg., Juvenile Corrections, St. Anthony, Idaho | B & S Boiler | $41,000 | 7-8-03 | |
| 6-16-03 (ak) | 03-203 Soccer Field Improvements, BSU, Boise, Idaho | Wright Brothers | $211,330 | 1. $5,135 2. $954 |
|
| CSDI Construction | $233,300 | 1. $1,700 2. $500 |
|||
| K-J Corporation | $198,800 | 1. $5,000 2. $500 |
|||
| KEPHA Construction | $186,000 | 1. $4,821 2. $346 |
6-26-03 | ||
| 8-14-03 | Veterans Cemetery, Roadway/Wall Facing, Eagle ID | Masco | $822,250 | 1. -8,220 | |
| Guho Corp. | $563,000 | 1. -10,000 | 8-25-03 | ||
| Wright Bros. | $589,431 | 1. -8,710 | |||
| 6-12-03 | 01253 II, Gibb Hall Animal Lab Water Separation, University of Idaho, Moscow, Idaho | R M Mechanical | $38,105 | ||
| 3-H Mechanical | $35,377 | 7/17/03 | |||
| Hilliard Heating & Plumbing | $39,200 | ||||
| 6-12-03 | 01005 Microwave, Phase III, DOA, Idaho Falls to Salmon, Idaho | Clyde Burnside | $474,976 | ||
| Brookstone | $562,842 | ||||
| Mountain West | $739,300 | ||||
| American Towers | $359,387.50 | ||||
| R. E. Beck | $578,567 | ||||
| Richard Jordan | $414,196 | 7/7/03 | |||
| 6-12-03 | 03225 Renovate HVAC Systems,
Liberal Arts Building, ISU, Pocatello ID BIDS REJECTED, TO BE REBID |
Bingham Mechanical | $245,400 | 1. $9,200 | |
| B&S Boiler | $184,460 | 1. $14,000 | |||
| Economy Heating | $278,560 | 1. $8,871 | |||
| Lewis Corp. | $256,000 | 1. $8,760 | |||
| Atlas-Luwa Mechanical | $268,740 | 1. $9,390 | |||
| 6-12-03 (ak) | 03-222 Fire Alarm Upgrades, ISU, Pocatello, Idaho | Arco Electric | $149,500 | 1. $23,700 2. $21,700 3. $10,550 |
|
| Alarmco | $185,000 | 1. $73,000 2. $73,000 3. $46,000 |
|||
| Portneuf Electric | $143,000 | 1. $24,900 2. $24,900 3. $11,500 |
|||
| Mountain West Electric | $125,500 | 1. $17,330 2. $20,360 3. $8,300 |
6-24-03 | ||
| Wheeler Electric | $125,400 | 1. $17,200 2. $17,600 3. $8,600 |
|||
| Warbonnet Electric | $172,000 | 1. $29,000 2. $30,000 3. $14,100 |
|||
| 6-10-03 (ak) | 02-234 Repair Sidewalks/Steps Campus Wide, ISU, Pocatello, Idaho | DeWall Construction | $138,013 | 1. $26,370 2. $18,230 3. $58 Unit Price |
|
| Kiggins Concrete | $116,200 | 1. $41,450 2. $16,790 3. $200 Unit Price |
7-15-03 | ||
| RE Beck Construction | $151,281 | 1. $46,453 2. $26,749 3. $315 Unit Price |
|||
| Taylor Quality Concrete | Non-Responsive | ||||
| Wellard Construction | $148,700 | 1. $50,820 2. $19,570 3.$60 Unit Price |
|||
| 5-16-03 (ak) | 02-216 New Residence Hall, Phase II, BP#25R, Boise State University, Boise, Idaho | Siemens | $520,859 | 1. $12,962 2. Incl. in Base Bid 3. $935 |
|
| Johnson Controls | $474,750 | 1. $11,675 2. $ 582 3. $ 192 |
5-20-03 | ||
| 5/14/03 | 03-208 Climbing Wall, Boise State University, Boise, Idaho | Nicros | $242,418 | 1. $32,000 2. $39,970 |
6/23/03 |
| Rockwerx | $220,400 | 1. $30,800 2. $15,000 |
|||
| ANCO | $268,800 | 1. $28,400 2. $27,000 |
|||
| 4/22/03 | 00355 I, Infrastructure, Veterans Cemetery, Eagle, Idaho | MRT | $2,351,650 | 1. $431,333 | |
| DeAtley Construcion | $1,686,950 | 1. $296,449 | |||
| Guho Corp. | $1,596,000 | 1. $294,000 | 6/2/03 | ||
| Masco Inc. | $1,765,000 | 1. $356,000 | |||
| Western Construction | $1,640,000 | 1. $330,000 | |||
| 10-29-03 | 03-063 Replace Locking System, Unit 7, Dept. of Correction, ISCI, Boise, Idaho | Southern Steel Company | $276,998 | 1. No Bid 2. $18,700 |
|
| Architectural Building Supply | $259,500 | 1. N/A 2. $15,700 |
11-4-03 | ||
| 11-4-03 (ak) | 04-191 Reroof Kinesiology Bldg., BSU, Boise, Idaho | Intermountain Roofing Company | $80,629 | 1. $16,674 2. $ 2,940 |
|
| Contract West Roofing | $85,100 | 1. $14,500 2. $ 4,300 |
|||
| Roman Roofs | $69,151 | 1. $17,266 2. $ 5,584 |
|||
| Upson Company | $69,779 | 1. $11,912 2. $ 2,808 |
|||
| Summit Associates | $65,200 | 1. $12,200 2. $ 4,100 |
11-12-03 | ||
| Modern Roofing | $82,069 | 1. $16,739 2. $ 2,880 |
|||
| Pro Tech Roofing | $71,526 | 1. $10,140 2. $ 2,625 |
|||
| Hobson Fabricating | $82,327 | 1. $15,810 2. $ 2,606 |
|||
| 11-5-03 (ak) | 03-511 A/V Upgrade, POST Academy, Idaho State Police, Meridian, Idaho | Marshall Industries, Inc. | Non-Responsive | ||
| AATronics, Inc. | $17,540.75 | 1. $17,540.75 2. $ 809.32 3. $ 2,125.42 4. $ 6,856.98 |
11-12-03 | ||
| Nimbus 360/UMC | $16,401.15 | 1. $15,561.15 2. $ 915.60 3. $ 5,886.00 4. $ 6,240.00 |
|||
| Marshall Industries, Inc. | $22,121 | 1. $20,714 2. $ 1,294 3. $ 3,250 4. $ 9,722 |
|||
| 11-5-03 (ak) | 02-401 Install Emergency Boiler, SHS. Blackfoot, Idaho | Ace Mechanical | $72,175 | ||
| B & S Boiler | $78,880 | ||||
| Bingham Mechanical | $49,200 | 11-18-03 | |||
| Economy Heating | $469,377 | ||||
| Atlas Mechanical | $88,730 | ||||
| Rivers West Construction | $86,000 | ||||
| Superior Boiler | $57,889 | ||||
| 11-6-03 | 03-252 Replace Air Handler #4, Animal Lab, University of Idaho, Moscow, Idaho | 3-H Mechanical | $85,427 | 1. $94,954 | |
| RM Mechanical | $100,615 | 1. $187,880 | |||
| 11-13-03 | 03-069 SICI Annex, Ag Bldg. Renovation, Boise, Idaho | CSDI | $663,200 | 1. $47,700 2. $ 3,600 |
|
| Ewing Company | $659,000 | 1. $47,700 2. $ 4,134 |
|||
| Guho Corp. | $641,950 | 1. $36,700 2. $ 3,450 |
11-21-03 | ||
| Scott Hedrick Construction | $641,000 | 1. $47,000 2. $ 3,400 |
|||
| K-J Corporation | $653,300 | 1. $35,000 2. $ 4,000 |
|||
| McAlvain Construction | $647,131 | 1. $37,414 2. $ 3,512 |
|||
| SE/Z Construction | $644,985 | 1. $44,692 2. $ 6,075 |
|||
| Valley Design & Construction | $729,000 | 1. $48,600 2. $ 2,700 |
|||
| 11-14-03 (ak) | 04-170 Reroof Siebert Hall NIC, Coeur d'Alene, Idaho | Pacific Tech | $211,000 | ||
| Cobra | $182,787 | 11-21-03 | |||
| 11-14-03 | 01-062 Replace Generator, ISCI, Boise, Idaho | Tri State Electric | $372,340 | ||
| Doherty Electric | $294,900 | ||||
| Quality Electric | $297,500 | ||||
| Challenger Electric | $286,000 | 11-19-03 | |||
| Electric Service & Contracting | $314,270 | ||||
| Enterprise Electric | $344,588 | ||||
| 11-18-03 | 03-062 Replace Locking System, CORR, IMSI & ICIO, Boise & Orofino, Idaho | Norment Security Group | $3,002,800 | 1. $ 6,750 2. $30,500 3. $30,500 4. $87,400 5. $63,000 |
|
| Engineered Control Systems | $2,873,378 | 1. $ 9,593 2. $13,614 3. $48,870 4. $84,743 5. $42,741 |
11-20-03 | ||
| 11-19-03 (ak) | 04-131 Chiller
Replacement, Christofferson Bldg., EITC, Idaho Falls, Idaho |
Bingham Mechanical | $48,977 | ||
| B & S Boiler | $48,776 | 11-26-03 | |||
| Ace Mechanical | $44,065 | ||||
| 11-25-03 (ak) | 02257 Power Plant Maintenance, UOI, Moscow, Idaho | 3-H Mechanical | $632,237 | 1. $90,202 2. $106,830 3. $8,347 4. $4,404 5. $9,195 |
12-8-03 |
| RM Mechanical | $732,400 | 1. $84,305 2. $103,300 3. $11,165 4. $10,160 5. $9,500 |
|||
| 12-4-03 | 03440 Window/Door Replacement, H & W, CDC / MH Bldgs, Reg V, Twin Falls, Idaho | Don Anderson Construction | $52,980 | ||
| Gary D. Jones Construction Co. | $48,987 | ||||
| Hayes Construction Co. | $42,329.28 | 12-15-03 | |||
| 12/9-03 | 03050 Backup Generator, State Controllers Office, Boise, Idaho | Enterprise Electric | $197,660 | 1. $12,050 | |
| Anderson & Wood Construction | $238,600 | 1. $13,800 | |||
| Doherty Electric | $193,685 | 1. $11,800 | 12-10-03 | ||
| Northwest Electrical | $197,990 | 1. $11,475 | |||
| Tri-State Electric | $199,800 | 1. $11,825 | |||
| Lea Electric | $216,000 | 1. $13,548 | |||
| Power Electric, Inc. | $234,552.56 | 1. $13,098 | |||
| Arco Electric | $211,540 | 1. $12,400 | |||
| 12-9-03 | 01194 West Campus Academic Bldg., BP23R, Boise State University, Nampa, Idaho | The Bledsoe Group | $30,250 | 1-5-04 | |
| Interior Systems | $53,012 | ||||
| 12-11-03 (ak) | 03600 West Wing Interior Remodel, Veterans Services, Boise, Idaho | Brice Construction | $166,400 | 1. $78,300 2. $10,500 |
1-5-04 |
| K-J Corporation | $211,000 | 1. $39,800 2. $ 8,350 |
|||
| 12-16-03 (ak) | 02512 POST Academy Training Facility, ISP, Meridian, Idaho | McAlvain Construction, Inc. | $1,531,310 | 1. $18,131.07 2. $ 79,429 3. $ 46,577 4. $ 20,224 5. $ 29,984 6. $ 923 7. $ 6,690 8. $ 4,936 9. $ 31,930 10. $17,799 11. $16,057 |
|
| Steed Construction | $1,542,500 | 1. $ 17,491 2. $ 74,592 3. $ 43,741 4. $ 18,992 5. $ 30,829 6. $ 558 7. $ 5,624 8. $ 5,358 9. $ 31,806 10. $16,715 11. $11,564 |
|||
| SE/Z Construction | $1,511,549 | 1. $18,430 2. $ 49,336 3. $ 21,926 4. $ 21,926 5. $ 33,454 6. $ 2,122 7. $ 7,025 8. $ 5,154 9. $ 38,084 10. $15,045 11. $16,367 |
12-31-03 | ||
| Bateman-Hall Construction | $1,612,900 | 1. $ 24,500 2. $ 52,000 3. $ 23,000 4. $ 23,000 5. $ 28,000 6. $ 2,500 7. $ 7,500 8. $ 6,500 9. $ 53,500 10. $16,000 11. $18,000 |
|||
| Scott Hedrick Construction | $1,498,138 | 1. $ 26,200 2. $ 82,600 3. $ 44,700 4. $ 30,300 5. $ 33,000 6. $ 2,600 7. $ 6,500 8. $ 7,000 9. $ 35,000 10. $18,500 11. $15,000 |
|||
| Valley Design & Construction | $1,567,000 | 1. $ 28,300 2. $ 77,400 3. $ 45,400 4. $ 19,700 5. $ 51,400 6. $ 580 7. $ 7,100 8. $ 5,600 9. $ 33,600 10. $17,400 11. $17,700 |
|||
| Contractors Northwest | $1,697,000 | 1. $ 22,790 2. $ 76,040 3. $ 44,590 4. $ 19,361 5. $ 22,544 6. $ 570 7. $ 7,797 8. $ 7,581 9. $ 33,100 10. $17,039 11. $15,636 |
|||
| The Ewing Company | $1,519,000 | 1. $ 29,745 2. $ 76,765 3. $ 45,015 4. $ 19,545 5. $ 24,566 6. $ 575 7. $ 5,860 8. $ 5,726 9. $ 31,675 10. $17,200 11. $15,575 |
|||
| CSDI Construction | $1,553,300 | 1. $ 30,100 2. $ 76,400 3. $ 44,000 4. $ 19,500 5. $ 22,400 6. $ 1,100 7. $ 5,800 8. $ 6,460 9. $ 32,700 10. $17,100 11. $15,500 |
|||
| Starr Corporation | $1,548,500 | 1. $ 18,000 2. $ 47,900 3. $ 21,300 4. $ 21,300 5. $ 25,200 6. $ 2,100 7. $ 7,000 8. $ 6,100 9. $ 34,400 10. $14,600 11. $11,300 |
|||
| Ormond Builders | $1,564,688 | 1. $ 21,468 2. $ 49,748 3. $ 22,110 4. $ 22,110 5. $ 25,881 6. $ 2,141 7. $ 6,082 8. $ 5,197 9. $ 35,750 10. $15,171 11. $15,653 |
|||
| Wright Brothers | $1,628,494 | 1. $29,031.74 2. $86,487.48 3. $46,792.64 4. $31,736.39 5. $33,868.35 6. $ 2,500.98 7. $ 8,237.69 8. $ 6,132.00 9. $61,831.37 10.$19,143.89 11.$11,888.42 |
|||
| K-J Corporation | $1,548,000 | 1. $ 33,000 2. $ 48,000 3. $ 22,000 4. $ 22,000 5. $ 23,000 6. $ 3,000 7. $ 10,000 8. $ 5,000 9. $ 25,000 10. $15,500 11. $13,500 |
|||
| Perkins Construction | $1,700,000 | 1. $ 27,000 2. $ 62,000 3. $ 33,000 4. $ 20,000 5. $ 13,000 6. $ 2,000 7. $ 4,000 8. $ 6,000 9. $ 60,000 10. $18,000 11. $15,000 |
|||
| 12-18-03 | 00355 III State Veterans Cemetery, Veterans Services, Boise, Idaho | Wright Brothers | $3,603,373 | 1. $ 63,360 2. $ 40,736 3. $100,233 4. $ -0- |
|
| SE/Z Construction | $3,467,939 | 1. $31,287 2. $30,450 3. $83,432 4. $34,108 |
|||
| McAlvain Construction | $3,669,211 | 1. $ 63,485 2. $ 31,800 3. $100,000 4. $121,200 |
|||
| Guho Corporation | $3,558,000 | 1. $40,400 2. $37,200 3. $97,000 4. $88,700 |
02-04-04 | ||
| The Ewing Company | $3,512,000 | 1. $ 61,056 2. $ 37,320 3. $ 80,695 4. $141,079 |
|||
| 12-18-03 (ak) | 04250 Reroof
Buchanan Engineering Lab, UOI, Moscow, Idaho ALL BIDS REJECTED due to irregularities on the bid documents - will be rebid at a later date. |
Missoula Sheet Metal & Roofing | $158,553 | 1. $229,662 | |
| Cobra Roofing Services | $148,644 | 1. $247,735 | |||
| Hobson Corp. | $165,101 | 1. $543,464 | |||
| Gillespie Roofing | $173,325 | No Bid | |||
| Icon Corp | $132,345 | No bid | |||
| 12-23-03 (ak) | 98240B Performing Arts Center, Concert Hall Finishes, ISU, Pocatello, Idaho | Safway Steel Products | $119,999 | 1. -$1,350 |
|
| Brand Scaffold | $135,829 | 1. +$7,960 | 1-16-04 | ||
| 12-30-03 | 04194 Primary Switchgear Modification, BSU, Boise, Idaho | Tri State Electric | $19,499 | ||
| Quality Electric | $27,266 | ||||
| Romar Electric | $17,148 | 1-6-04 | |||
| MRK Electric | $22,275 | ||||
| Electric Service | $24,609 | ||||
| Anderson & Wood Construction | $24,870 | ||||
| Power Plus | $21,674 | ||||
| 10-21-03 (ak) | 99-092 Fine Arts Addition, College of Southern Idaho, Twin Falls, Idaho | For Bid Results,
contact STAR Corporation at (208) 733-5695 |
|||
| 10-16-03 (ak) | 04-360 Reroof Laundry Bldg., ISSH, Nampa, Idaho | Roman Roofs, Inc. | $51,801 | ||
| Quality Tile Roofing, Inc. | $53,182 | ||||
| Hobson Fabricating | $64,537 | ||||
| Western Roofing | $47,840 | 10-23-03 | |||
| Modern Roofing | Non-responsive | ||||
| Pro-Tech Roofing | $49,977 | ||||
| Summit Associates | $56,840 | ||||
| Upson Company | $49,508 | ||||
| 10-14-03 (ak) | 98-240B, ISU: PERFORMING ARTS CENTER, Idaho State University, Pocatello, Idaho | For bid results SLETTEN CONSTRUCTION CO INC: (208) 658-9888 | |||
| 10-14-03 (ak) | 03-210 Weight Room Expansion, BSU, Boise, Idaho | Wright Brothers | $453,397 | ||
| Guho Corporation | $449,400 | ||||
| Dave Allen Construction | $409,139 | 10-21-03 | |||
| Scott Hedrick Construction | $406,999 | ||||
| K-J Corporation | $414,500 | ||||
| CSDI Construction | $444,200 | ||||
| McAlvain Construction | $409,859 | ||||
| Ewing Company | $438,500 | ||||
| Perkins Construction | $415,000 | ||||
| 10-9-03 | 02-337 Armory Renovation, PH II, Military Division, Lewiston, Idaho | Kenaston Corporation | $124,229 | 1. $3,085 2. $13,276 3. $18,682 4. $6,735 5. Not Used 6. $5,000 |
|
| Teel Construction | $161,075 | 1. $1,911 2. $9,437 3. $12,298 4. $7,404 5. Not Used 6. $3,870 |
|||
| S & W Construction | $121,900 | 1. $1,500 2. $8,300 3. $13,000 4. $14,300 5. Not Used 6. $5,175 |
10-21-03 | ||
| A & R Construction | $128,999 | 1. $2,434 2. $8,912 3. $14,687 4. $5,934 5. Not Used 6. $5,175 |
|||
| W C Construction | $143,000 | 1. $5,000 2. $13,000 3. $12,000 4. $11,000 5. Not Used 6. $6,000 |
|||
| 10-8-03 | 04-130 Doors/Windows, Sessions Bldg., EITC, Idaho Falls, Idaho | Vern Clark & Sons | $128,992 | 1. $14,400 2. $13,500 3. $9,600 4. $$28,500 5. $3,200 6. $10,400 |
10-21-03 |
| Larry Chapple Construction | $156,099 | 1. $13,444 2. $10,400 3. $9,300 4. $ 25,241 5. $2,621 6. $10,738 |
|||
| 10-6-03 (ak) | 03-225, Renovate HVAC Systems, Liberal Arts Bldg., ISU, Pocatello, Idaho | Atlas Mechanical | $144,280 | 1. $25,990 2. $46,330 |
|
| Bingham Mechanical | $110,500 | 1. $12,300 2. $46,800 |
10-9-03 | ||
| B & S Boiler | $116,425 | 1. $13,421 2. $49,144 |
|||
| Economy Heating | $129,796 | 1. $17,511 2. $47,807 |
|||
| Lewis Corp. | $119,300 | 1. $12,430 2. $47,360 |
|||
| Ace Mechanical | $121,083.03 | 1. $9,952.18 2. $42,396.66 |
|||
| 9-23-03 (ak) | 03-331 Site Improvements, Blackfoot Armory, Military Division, Blackfoot, Idaho | Bateman Hall | $149,500 | ||
| Ferguson 4T | $144,600 | ||||
| Gale Lim Construction | $119,411.23 | 9-25-03 | |||
| Kiggins Concrete | $144,000 | ||||
| Holmes | $146,165 | ||||
| Dig 'Em Up | $169,000 | ||||
| Parsons | $162,800 | ||||
| 9-23-03 (ak) | 02-302 3rd St. Annex Remodel, Dept. of Labor, Boise, Idaho | Kepha | $156,973 | 1. $9,391 2. $19,780 3. $2,529 |
|
| Don Young Construction | $149,250 | 1. $9,400 2. $14,150 3. $4,060 |
|||
| Gafford Construction | $153,911 | 1. $10,018 2. $13,728 3.$5,347.99 |
|||
| K-J Corp. | $139,874 | 1. $7,800 2. $18,900 3. $3,000 |
10-1-03 | ||
| McAlvain Construction | $169,360 | 1. $6,900 2. $16,750 3. $4,875 |
|||
| Perkins Construction | $158,600 | 1. $9,200 2. $14,600 3. $3,500 |
|||
| Wright Brothers | $161,492 | 1. $7,165 2. $13,194 3. $3,801 |
|||
| 9-16-03 (ak) | 01-332 Renovate Blackfoot Armory, Military Division, Blackfoot, Idaho | Bateman-Hall | $44,400 | 8-5-03 | |
| Vern Clark & Sons | $26,195 | ||||
| Gate City | $30,785.71 | ||||
| 9-16-03 | 95-764 Well No. 4 Pumping Facilities, Bid package No. 9 - Phase 2, SICI, Boise, Idaho | Drake Mechanical | $237,711 | ||
| Riverside Inc. | $228,897 | ||||
| Irminger Const. | $236,397 | ||||
| 8-29-03 | 02-258 Water Reclaimed Line - UCC/Library Location, University of Idaho, Moscow, Idaho | Albright & Sons | $24,315 | ||
| RM Mechanical | $29,273 | ||||
| 8-26-03 | 01-222 Classroom/Multi-Use Complex, ISU, Pocatello, Idaho | For bid results, please contact Construction Manager, Brennan Construction @ (208) 232-5021 | |||
| 8-19-03 | 01-152 Elevator/Access/Restroom Addition, Old Science Building, LCSC, Lewiston, Idaho | Kenaston Corp. | $591,760 | ||
| Leone & Keeble | $663,000 | ||||
| 7-31-03 (ak) | 99-092 Rebid, Fine Arts Addition, College of Southern Idaho, Twin Falls, Idaho | For bid results click Starr Corp or at (208) 733-5695 | |||
| 6-25-03 (ak) | 01-256 New Elevator, P.E. Bldg., University of Idaho, Moscow, Idaho | Wimer Corporation | $383,720 | 1. $4,000 2. $9,500 3. $1,780 |
9-24-03 |
| Contractors NW, Inc. | $368,191 | 1. $3,865 2. $9,504 3. $975 |
|||
| Kenaston Corporation | $463,800 | 1. $4,380 2. $4,250 3. $1,400 |
|||
| CAMCO Construction | $395,486 | 1. $10,000 2. $9,559 3. $984 |
|||
| Citadel Construction, Inc. | $499,000 | 1. $5,000 2. $10,000 3. $1,200 |
|||
| A & R Construction | $452,000 | 1. $3,500 2. $2,100 3. $1,100 |
For more information regarding this page, please email Construction Management at 208.332.1900.